Engage Planner

Planner is part of Engage. You use it to set the priority order of operations on a resource, week by week. When you publish the plan, operators see the operations in that order in Schedule, where they start and report their work.

Each row in the plan is one operation, a single step of a production order, such as setup or machining. You can drag operations into a new order and move them between weeks. When you are done, save the plan as a draft or publish it.

To open Planner, go to Engage > Planner in the left navigation.

Engage menu with Schedule and Planner

Who can use this

Planner is shown to users with the MES Planner or Admin role. Schedule is shown to users with the MES Reader, MES Operator or Admin role. A user who only has MES Planner sees Planner, but not Schedule. See Access Control.

How it fits together​

  1. The plan for a resource starts from the ERP plan, which is the sequence your ERP system provides.
  2. You reorder operations, move them between weeks, and lock the sequence as needed.
  3. You save a draft to keep your work in progress, or publish to send the new sequence to Schedule.
  4. Schedule shows the last published plan. After a reset, it shows the ERP plan. Saving or discarding a draft does not change Schedule.
  5. Every save, publish and reset is kept as a version. You can open and restore versions at any time.

Select a resource​

A plan belongs to one resource. Choose the resource in the resource selector at the top left. Your favorite resources are listed first in the selector.

Resource selector at the top of Planner

Read the plan​

The plan is a list of operations grouped by week. The current week and the next three weeks are always shown, even when they are empty. Later weeks are shown when they contain operations.

How operations are placed​

Planner places operations in the plan automatically:

  • By planned start date: each operation is placed in the week of its planned start date from the ERP. If you move an operation to another week, it stays there, even if the date in the ERP changes. If it is not completed by the end of the week, it moves to the next week.
  • Past planned start dates: an operation whose planned start date has already passed is placed in the current week.
  • Unfinished operations: when a week ends, the operations in it that are not completed are moved to the top of the next week.
  • New operations from the ERP: a new operation is placed in the week of its planned start date, below any locked operations in that week. If its planned start date has passed, it goes into the current week, also below any locked operations. New operations are highlighted in the plan (see Row highlights).

Week headers​

Each week starts with a header row:

FieldMeaning
WeekThe ISO week number.
CapacityThe hours available on the resource that week.
ReservedThe hours of remaining work planned for that week.
AvailableCapacity minus reserved hours. Shown in red when the week is overloaded.

The colored dot next to the week number shows the load at a glance:

  • Blue: under 90% of capacity
  • Green: 90–100% of capacity
  • Red: over capacity
  • Gray: the resource has no shift plan. The week header then shows only Reserved.

Hover over the week number to see the dates of the week and a capacity breakdown.

How capacity is calculated

Capacity comes from the shift plan for the resource in Settings. For the current week, only the time left in the week is counted, so capacity goes down as the week passes.

Week header with capacity, reserved and available hours

Columns​

ColumnWhat it shows
#The position of the operation in the sequence. You can edit it (see Type a new position).
StartThe planned start date, or the actual start or end if the operation has started.
StatusWhether the operation is ready to start, and whether it is in progress.
OperationOperation number and name. Setup operations are marked (Setup).
OrderThe production order number. Select it to open the production order.
TimeOperation time.
QuantityPlanned, started, produced and scrapped quantities.
ProjectProject number, with the BOM position if there is one. Hover to see the project name.
PartPart number and name, with a button that copies the part number.
ProgramThe CNC program status (see Program status).
MaterialPart material.
ResourceResource ID. Hover to see the resource name and department.

On the far right of each row:

  • The notes icon opens the discussion for the operation. The icon is highlighted when there are notes, and a dot shows when there are unread notes. Messages you write here are tagged as Planner notes.
  • The expand toggle shows the full operation details below the row.

Operation details expanded below a row

Row highlights​

HighlightMeaning
Purple bar on the left (orange in dark mode)The row is locked in the sequence.
Purple tinted background (orange in dark mode)You have moved the row and not saved yet.
Light blue backgroundA new operation from the ERP that is not in the saved plan yet and is not locked.

Locked, moved and new rows in the plan

Change the sequence​

Drag operations​

Drag an operation by its handle to a new position. The operation moves into the week of the row you drop it below.

To move several operations at once, select them first and then drag one of them. The whole selection moves together and keeps its order.

To selectWindowsMac
A range of operationsClick the first, then Shift+click the lastClick the first, then Shift+click the last
Individual operationsCtrl+click each oneCmd+click each one

Selecting several operations and dragging them to a new position

Type a new position​

  1. Double-click the # cell of an operation.
  2. Type the new position.
  3. Press Enter.

The operation moves to that position and into the week of the row it lands next to. If the number is outside the plan, the operation goes to the first or last position.

Lock the sequence​

To lock the sequence, right-click an operation and select Lock sequence up to this row. That row and every row above it are locked. If the row is already locked, the menu shows Already locked.

Operations you move are locked too, along with every row above them. The bar on the left shows which rows are locked.

Everything above the lowest row you have moved or locked is locked.

Lock sequence up to this row in the right-click menu

Undo, redo and reset​

The buttons at the top right let you step through your changes before you save:

ButtonShortcutWhat it does
UndoCtrl+Z / Cmd+ZReverses your last change.
RedoCtrl+Y / Cmd+Shift+ZReapplies a change you undid.
ResetCtrl+R / Cmd+RRemoves all unsaved changes and goes back to the loaded plan.

Undo, Redo, Reset, Discard draft, Save draft, Versions and Publish buttons

Save and publish​

Save a draft​

  1. Click Save draft (Ctrl+S / Cmd+S).
  2. Optionally, add a comment in the Save draft dialog.
  3. Click Save draft.

A draft is personal. Only you can see it, both in the plan and in the version history. Other planners and operators do not see your changes until you publish. You can come back to your draft later.

Publish​

  1. Click Publish (Ctrl+Enter / Cmd+Enter).
  2. Optionally, add a comment in the Publish plan dialog, for example the reason for the change. The comment is shown in the version history.
  3. Click Publish.

The plan becomes the active sequence, and operators see the new order in Schedule right away. If you have unsaved changes, they are saved as part of publishing.

Publish plan dialog with an optional comment

Discard a draft​

Click Discard draft (Ctrl+D / Cmd+D) to remove your saved draft and go back to the last published plan. The button is only available when you have a draft.

Unsaved changes​

The plan reloads every two minutes, so you see changes from others and from the ERP. Reloading is paused while you have unsaved changes.

If you switch resource, open another version or leave the page with unsaved changes, you are asked to confirm before your changes are discarded.

Program status​

The Program column shows whether the CNC program for an operation is ready. It has two icons:

  • ✅ Program ok (green when selected): the program is ready.
  • ❌ Program not ok (red when selected): the program is not ready.

Click an icon to set the status. Click the selected icon again to clear it.

The program status is saved immediately and is not part of the draft or the published plan. You cannot change it while you are viewing a previous version.

Versions​

Click Versions to open the version history for the selected resource in the Planner Versions panel. Each entry shows:

  • The event type:
    • Published
    • Draft saved (only your own drafts are shown)
    • Reset to ERP
  • When it happened, and who did it
  • The comment, if one was added
  • The number of operations in the plan

The version you are viewing is marked Viewing.

Planner Versions panel with published and draft versions

View and restore a previous version​

Select a version in the list to open it. A banner shows that you are viewing a previous version. Click Back to latest to return to the latest version.

While you view a previous version, you can still reorder operations. To restore the version, save it as the latest version:

  • Save draft restores the version as a draft. Schedule does not change until you publish.
  • Publish restores the version as the published plan and updates Schedule.

Banner shown when viewing a previous version

Reset to the ERP plan​

Click Reset to ERP plan at the top of the Planner Versions panel to remove all planning and start again from the sequence provided by the ERP.

warning

Resetting to the ERP plan discards your own draft, if you have one, and the published plan for the resource. Schedule goes back to the ERP sequence straight away. Drafts from other planners are not affected. The reset is recorded in the version history as Reset to ERP.

Keyboard shortcuts​

ActionWindowsMac
UndoCtrl+ZCmd+Z
RedoCtrl+YCmd+Shift+Z
Reset unsaved changesCtrl+RCmd+R
Save draftCtrl+SCmd+S
Discard draftCtrl+DCmd+D
PublishCtrl+EnterCmd+Enter